Premier League Rugby Stadium

Members of the QSPM team have worked with Exeter Rugby Club CEO, Tony Rowe, over two phases of development for the Exeter Chiefs.

Phase 1 required Project Management and Cost Consultancy services for the County Ground disposal, Partner procurement, Relocation planning and provision of a new  stadium and conference facilities at Sandy Park. The project consisted of a 10,000 seat Stadium and associated public and players facilities.

Phase 2 consisted of extending the existing West Stand to provide additional covered seating increasing the stadium capacity to 20,600 seats, as well as construction of larger conference rooms / banqueting suites. Since the stadium was required to remain operational throughout the works complex phasing and planning of the project was required to minimise disruption during construction.

Phase 1

Value: £8 million

Completion: September 2008

Procurement route: A JV with a tendered preferred developer. The NEC 3 Fixed Price single stage with Design contract was used to give certainty of costs with minimal risks to the Client. Identifying cost certainty at the point of contract award and better control of quality and contractor’s on site activities were key benefits.

Role: Individual members of the QSPM Team acted as Project Manager, Employer’s Agent and Cost consultants for the Pre and Post Contract Stages.

Phase 2

Value: £6.6 million

Completion: September 2014

Procurement route: Single stage Design and Build, using the NEC 3 suite of contracts.

Role: QSPM Team acted as Project Manager, Employer’s Agent and Cost consultants for both Pre and Post Contract Stages.

Sector: Stadia, Sports and Leisure

 

  Image credits: Kensington Taylor Architects